Important: Several street closures are planned as part of other construction projects underway in the vicinity. To remain updated, be sure to check the New Vic website for all details.
Construction start:ÌýDecember 2022
Planned construction end:ÌýDecember 2024
µþ³Ü»å²µ±ð³Ù:Ìý$42,501,000
As part of the creation of the Sylvan Adams Sports Science Institute, announced on August 31, 2022, Â鶹AV will transform four of its row houses on Pine Avenue into a complex comprising state-of-the-art testing labs, training suites, research offices, and meeting rooms. The row houses are located between the Montreal Neurological Institute and the Sir Arthur Currie Memorial Gymnasium.
The project consists of building a back extension to the four row houses and an adjoining fifth house, and restoring a large part of their overall existing volume as well as the four front façades. Necessary upgrades to bring the facility up to building codes, including for seismic resistance and universal access, are also planned as is the replacement of the HVAC, electrical and water distribution systems.
More information on the Sylvan Adams Sports Science Institute:Ìýmcgill.ca/sassi
What to expect
Date | Work | Impact |
---|---|---|
Fall 2022 - Fall 2023 | Selective demolition and excavation, replacement of underground services, structural work |
Increased vehicle trafficÌýto and from construction site, including cranes and large vehicles Medium to high levels of noise, particularly close to the site Pedestrian traffic possibly restricted to south sidewalk for a limited period of time Pedestrian traffic possibly restricted to south sidewalk |
Fall 2023 - Fall 2024 | Interior work, structural work | Increased circulation of vehicles to and from construction site |
Fall 2024 | Asphalting in the back of the facility and landscaping |
Asphalt odours Work happening exclusively within the site perimeter |
Ìý